
Project Overview
For this project, Debono Bros were set the task of completing a three story concrete structure that would be used as classrooms for years 7-10.
Materials Used
– 280 tonnes of reinforcement
– 2,350m3 of concrete
Our Contract
– 3,000m3 soil removal
– 1,700m2 ground slab
– 1,700m2 level 1 slab
– 1,700m2 level 2 slab
– 3 sets of tiered viewing seats
– 4 internal concrete stairs